Click to scroll through this photo collection.
Calaveras Dam Replacement, horizontal scaffold pipes. Calaveras Dam Replacement, Calaveras Dam outlet tower construction. Scans from Calaveras Dam Album No. 8 Calaveras Dam, Discharge pipes and penstock into 20″ well, looking southeast. Calaveras Dam Replacement, installing rebar to the new Calaveras pipeline, 7′ diameter pipe that will be completely buried in the new dam that connects directly to the outlet structure already in place in the existing dam. This pipe will transport our drinking water supply from the Calaveras Reservoir to the Sunol Valley Water Treatment Plant and then on to our 2.6 million Bay Area customers when supplies are needed. The team plans to connect the new 78 inch pipe to the existing pipes within the existing dam in Fall 2016.